On scratch paper, build the following network diagram...What is the total float of Activity?
On scratch paper, build the following network diagram
• Activity A (2 days) can start right away.
• Activity B (3 days) and Activity C (4 days) can start after Activity A is finished.
• Activity D (5 days) can start after Activity B is finished.
• Activity E (1 day) and Activity F (4 days) can start after Activity C is finished.
• Activity G (2 days) can start after Activity E is finished.
• Activity H (3 days) can start after Activity F is finished.
• Activity I (2 days) can start after Activity D, Activity G and Activity H are finished.
• After Activity I is finished, the project is complete.
What is the total float of Activity?
Correct Answer : A