Rob must estimate the minimum project duration. What schedule network analysis technique should he use?
Rob must estimate the minimum project duration. What schedule network analysis technique should he use?
A- automated string analysis
B- total float estimation
C- critical path method.
D- network path calculation.
Correct Answer : C