The critical chain method (CCM) is
The critical chain method (CCM) is
A- analogous to the critical path method.
B- a schedule network analysis technique that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
C- any activity that is on the critical path.
D- none of the above
Correct Answer : C