The initiating process group includes
The initiating process group includes
A- those processes required to tract, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes.
B- those processes performed to complete the work defined in the project management plan to satisfy the project specifications.
C- those processes performed to finalize all activities across all process groups to formally close the project or phase.
D- those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.
Correct Answer : D