You are responsible for managing a project that deals with laying out a freeway connecting two major port cities

You are responsible for managing a project that deals with laying out a freeway connecting two major port cities.Progress on the project has been smooth and you and your team are very confident on completing the project well within the stipulated timelines.On reviewing you see that the project has also run below the budget resulting in savings.You decide to add an extra feature of reflector strips on the road every mile.You do a quick calculation and are satisfied that neither budget nor schedule will slip.You feel that by adding these extra features you could also bag some future projects as well.This is an example of :
Correct Answer : B
This is an example of Gold Plating.Integrated change control deals with formally approving or rejecting changes before they are implemented so it is not the correct answer.Fast tracking is a schedule compression technique - so it too is not the correct answer.While Scope Creep is related to change in scope it is related to uncontrolled changes in product or projects scope and is often due to client interference.Gold plating is done intentionally or knowingly for some strategic purpose.Here the manager believes that by adding the extra features future projects could be bagged.