A baseline is
A baseline is
A- the time in calendar units between the start and finish of a schedule activity.
B- compared to desired project performance to evaluate project success.
C- a component of work performed during the course of the project.
D- compared to actual performance to determine if performance is within acceptable variance thresholds.
Correct Answer : D