Before being baselined, requirements should be
Before being baselined, requirements should be
A- approved by the project team.
B- rejected by the Change Control Board.
C- unambiguous (measurable and testable), traceable, complete, consistent, and acceptable to key stakeholders.
D- none of the above
Correct Answer : C