ground excavation project is expected to last for a period of four months. All project work must cease on rainy days. When preparing the project scope, the rain should be cited as

A ground excavation project is expected to last for a period of four months. All project work must cease on rainy days. When preparing the project scope, the rain should be cited as
Correct Answer : A