Jett Kayaks is adding a new manufacturing line and Brandon is the project manager. He estimated the cost of implementing the new manufacturing line at $47,300. He arrived at this amount by reviewing the WBS and adding together all estimates of the lower-level components. This method of estimating cost is called

Jett Kayaks is adding a new manufacturing line and Brandon is the project manager. He estimated the cost of implementing the new manufacturing line at $47,300. He arrived at this amount by reviewing the WBS and adding together all estimates of the lower-level components. This method of estimating cost is called
Correct Answer : C