The critical chain method is
A- the sequence of schedule activities that determines the duration of the project.
B- a schedule network analysis technique used to determine the amount of scheduling flexibility (the amount of float) on various network paths.
C- a schedule network analysis technique that modifies the project schedule to account for limited resources.
D- none of the above
Correct Answer : C