The scope baseline for the project is
The scope baseline for the project is
A- set forth in the contract.
B- the initial project scope statement.
C- the approved version of the project scope statement, work breakdown structure (WBS) and the WBS dictionary.
D- found in the lessons learned documentation.
Correct Answer : C